NTS OGDCL (Oil & Gas) Mathematics Time & Work — Set 2

Time & Work MCQs set 2 for NTS OGDCL (Oil & Gas) Mathematics — 20 solved questions.

NTS OGDCL (Oil & Gas) Mathematics Time & Work — Set 2

  1. Question 1

    Q1. A tank is filled in 5 hours by three pipes A, B and C. The pipe C is twice as fast as B and B is twice as fast as A. How much time will pipe A alone take to fill the tank?

    • A) 20 hrs
    • B) 25 hrs
    • C) 35 hrs
    • D) Cannot be determined

    Answer: 35 hrs

    Explanation: Let A's rate = r; B = 2r, C = 4r; combined 7r = 1/5 → r = 1/35; A alone takes 35 hours.

  2. Question 2

    Q2. Pipes P and Q would fill a cistern 18 and 24 minutes respectively. Both pipes being opened, find when the first pipe must be turned off so that the cistern may be just filled in 12 minutes?

    • A) After 12 mins
    • B) After 9 mins
    • C) After 8 1/2 mins
    • D) After 10 mins

    Answer: After 9 mins

    Explanation: Q works all 12 min filling 12/24 = 1/2; P works t min filling t/18; t/18+1/2 = 1 → t = 9 minutes.

  3. Question 3

    Q3. A and B can do a piece of work in 21 and 24 days respectively.They start the work together and after some days, A leaves and B completes the rest of the task in 9 days. After how many days did A leave?

    • A) 5
    • B) 6
    • C) 7
    • D) 8

    Answer: 7

    Explanation: B completes 9/24 = 3/8 alone; remaining 5/8 done together at rate 1/21+1/24 = 15/168; time = (5/8)/(15/168) = 7 days.

  4. Question 4

    Q4. P can lay railway track between two stations in 16 days. Q can do the same job in 12 days. With the help of R, they completes the job in 4 days. How much days does it take for R alone to complete the work?

    • A) 9(3/5) days
    • B) 9(1/5) days
    • C) 9(2/5) days
    • D) 10 days

    Answer: 9(3/5) days

    Explanation: 1/P+1/Q+1/R = 1/4; 1/16+1/12+1/R = 1/4 → 1/R = 5/48; R alone takes 48/5 = 9⅗ days.

  5. Question 5

    Q5. If 25 men can eat 150 kg of wheat in 30 days then 45 men can eat 450 kg of wheat in how many days?

    • A) 13 days
    • B) 50 days
    • C) 15 days
    • D) 18 days

    Answer: 50 days

    Explanation: Rate = 150 kg/(25×30) man-days; for 45 men eating 450 kg: days = 450×25×30/(150×45) = 50 days.

  6. Question 6

    Q6. A tank is filled in eight hours by three pipes A, B and C. Pipe A is twice as fast as pipe B, and B is twice as fast as C. How much time will pipe B alone take to fill the tank?

    • A) 24 hours
    • B) 28 hours
    • C) 32 hours
    • D) 36 hours

    Answer: 28 hours

    Explanation: Let C's rate = x, then B = 2x and A = 4x; combined rate 7x fills in 8 hours so x = 1/56, and B alone (rate 2x = 1/28) takes 28 hours.

  7. Question 7

    Q7. A water tank is two-fifth full. Pipe A can fill a tank in 10 minutes and pipe B can empty it in 6 minutes. If both the pipes are open, how long will it take to empty or fill the tank completely?

    • A) 6 min. to empty
    • B) 6 min. to full
    • C) 9 min. to empty
    • D) 9 min. to full

    Answer: 6 min. to empty

    Explanation: Pipe B empties faster than A fills; net drain rate = 1/6 − 1/10 = 1/15 of the tank per minute. To empty 2/5 of the tank takes (2/5) × 15 = 6 minutes.

  8. Question 8

    Q8. A can do a piece of work in 6 days and B can do the same work in 12 days. How long will it take if A and B work together?

    • A) 4
    • B) 6
    • C) 8
    • D) 10

    Answer: 4

    Explanation: Combined work rate = 1/6 + 1/12 = 1/4 per day, so together they finish the work in 4 days.

  9. Question 9

    Q9. If 6 men can make 10 sofas in 2 days, then 8 men can make 8 sofas in__________?

    • A) 1.8 days
    • B) 1.5 days
    • C) 1.2 days
    • D) 1 day

    Answer: 1.2 days

    Explanation: Total work = 6 × 2 = 12 man-days for 10 sofas, so each sofa needs 1.2 man-days. Eight sofas need 9.6 man-days, and 8 men complete that in 9.6/8 = 1.2 days.

  10. Question 10

    Q10. Two pipes can fill a tank in 20 and 24 minutes respectively and a waste pipe can empty 3 gallons per minute. All the three pipes working together can fill the tank in 15 minutes. The capacity of the tank is?

    • A) 60 gallons
    • B) 100 gallons
    • C) 120 gallons
    • D) 180 gallons

    Answer: 120 gallons

    Explanation: Setting up the equation for 15-minute fill time with both inlet pipes and waste pipe gives a waste rate of 1/40 tank per minute = 3 gallons/min, so capacity = 120 gallons.

  11. Question 11

    Q11. 8 children and 12 men complete a certain piece of work in 9 days. If each child takes twice the time taken by a man to finish the work, in how many days will 12 men finish the same work?

    • A) 6 days
    • B) 8 days
    • C) 10 days
    • D) 12 days

    Answer: 12 days

    Explanation: Since each child takes twice a man's time, 8 children = 4 men, making a total of 16 men; 12 men will take 16×9/12 = 12 days.

  12. Question 12

    Q12. A can do a certain work-in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in_________?

    • A) 15 days
    • B) 20 days
    • C) 25 days
    • D) 30 days

    Answer: 25 days

    Explanation: Since A's rate equals B+C combined, and with C alone taking 50 days, working through the equations gives B alone taking 25 days.

  13. Question 13

    Q13. A is twice as good a workman as B and takes 6 less days to complete a piece of work as

    • A) 12 days
    • B) does. To finish the work alone, B will take: Time-Work 10 days
    • C) 13 days
    • D) 16 days

    Answer: 12 days

    Explanation: Since A is twice as productive as B, if B takes t days then A takes t/2 days; t − t/2 = 6 gives t = 12 days.

  14. Question 14

    Q14. A cistern is normally filled in 8 hours but takes two hours longer to fill because of a leak in its bottom. If the cistern is full the leak will empty it in. Pipes and Cisterns

    • A) 16 hrs
    • B) 20 hrs
    • C) 25 hrs
    • D) 40 hrs

    Answer: 40 hrs

    Explanation: Fill rate = 1/8 per hour; with the leak the net fill rate = 1/10 per hour, so the leak rate = 1/8 − 1/10 = 1/40, meaning it empties the cistern in 40 hours.

  15. Question 15

    Q15. A large tanker can be filled by two pipes A and B in 60 minutes and 40 minutes respectively. How many minutes will it take to fill the tanker from empty state if B is used for half the time and A and B fill it together for the other half?

    • A) 15 min
    • B) 20 min
    • C) 27.5 min
    • D) 30 min

    Answer: 30 min

    Explanation: If total time is T, pipe B alone for T/2 fills T/80, and A+B together for T/2 fills T/48; setting T/80 + T/48 = 1 gives T = 30 minutes.

  16. Question 16

    Q16. Two pipes X and Y fill a tank in 15 hrs. and 20 hrs. respectively, while a third pipe 'Z' can empty the full tank in 25 hrs. All the three pipes are opened in the beginning. After 10 hrs. Z is closed. In how much time, will the tank be full?

    • A) 12 hrs
    • B) 14 hrs
    • C) 16 hrs
    • D) 18 hrs

    Answer: 12 hrs

    Explanation: In 10 hours all three pipes fill 23/30 of the tank; the remaining 7/30 is filled by X and Y alone (rate 7/60 per hour) in 2 more hours, totalling 12 hours.

  17. Question 17

    Q17. A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. How many days would it take for A, B, and C to finish the work together?

    • A) 10 days
    • B) 12 days
    • C) 14 days
    • D) None of these

    Answer: 10 days

    Explanation: The correct value is 10 days. Apply the formula or arithmetic step shown in the question and

  18. Question 18

    Q18. If 3 men or 4 women can construct a wall in 43 days, then the number of days that 7 men and 5 women take to construct it is:

    • A) 12 days
    • B) 14 days
    • C) 16 days
    • D) 18 days

    Answer: 12 days

    Explanation: 3 men = 4 women in capacity, so 7 men + 5 women = 28/3 + 5 = 43/3 women. Total work = 4 × 43 = 172 woman-days. Days = 172 ÷ (43/3) = 12 days.

  19. Question 19

    Q19. If 6 men take 9 days to complete a work, how many men can complete the work in 3 days?

    • A) 2 men
    • B) 12 men
    • C) 9 men
    • D) 18 men

    Answer: 18 men

    Explanation: Total work = 6 × 9 = 54 man-days. To finish in 3 days, men needed = 54/3 = 18.

  20. Question 20

    Q20. A can do a piece of work in 10 days and B in 15 days. If they work for a day alternatively. A beginning the work will be completed in:

    • A) 6 days
    • B) 12 days
    • C) 8 days
    • D) 15 days

    Answer: 12 days

    Explanation: On day 1 A does 1/10 and day 2 B does 1/15; combined in each 2-day cycle = 1/10 + 1/15 = 1/6. Six such cycles (12 days) complete the entire work.

1/20
0
0
Level 1

A tank is filled in 5 hours by three pipes A, B and C. The pipe C is twice as fast as B and B is twice as fast as A. How much time will pipe A alone take to fill the tank?