If 6 men can make 10 sofas in 2 days, then 8 men can make 8 sofas in__________?
Q1. If 6 men can make 10 sofas in 2 days, then 8 men can make 8 sofas in__________?
Answer: 1.2 days
Explanation: Total work = 6 × 2 = 12 man-days for 10 sofas, so each sofa needs 1.2 man-days. Eight sofas need 9.6 man-days, and 8 men complete that in 9.6/8 = 1.2 days.