engineering intelligence MCQ #160

A, B, and C can do a work in 10, 15, and 20 days respectively. How many days will they take to complete the work together?

engineering intelligence MCQ #160

  1. Question 1

    Q1. A, B, and C can do a work in 10, 15, and 20 days respectively. How many days will they take to complete the work together?

    • A) 4.7 days
    • B) 5 days
    • C) 4 days
    • D) 6 days

    Answer: 4.7 days

    Explanation: Combined rate = 1/10 + 1/15 + 1/20 = (6 + 4 + 3)/60 = 13/60. Time = 60/13 = 4.6 days, rounded to 4.7.