engineering intelligence MCQ #182

If 8 men can reap a field in 15 days, how many men are needed to reap the same field in 10 days?

engineering intelligence MCQ #182

  1. Question 1

    Q1. If 8 men can reap a field in 15 days, how many men are needed to reap the same field in 10 days?

    • A) 10 men
    • B) 12 men
    • C) 15 men
    • D) 20 men

    Answer: 12 men

    Explanation: The work done is constant, so the product of men and days should be constant. 8 men * 15 days = 12 men * 10 days, so 12 men are needed.