A, B, and C can do a work in 10, 15, and 20 days respectively. How long will they take to complete the work together?

engineering intelligence MCQ #271

  1. Question 1

    Q1. A, B, and C can do a work in 10, 15, and 20 days respectively. How long will they take to complete the work together?

    • A) 4.7 days
    • B) 5 days
    • C) 4 days
    • D) 6 days

    Answer: 4.7 days

    Explanation: Their combined rate of work = 1/10 + 1/15 + 1/20 = (6 + 4 + 3)/60 = 13/60. So, time taken = 60/13 = 4.62 days.