engineering intelligence MCQ #276

A can do a work in 20 days. B is 25% more efficient than A. How long will B take to do the work?

engineering intelligence MCQ #276

  1. Question 1

    Q1. A can do a work in 20 days. B is 25% more efficient than A. How long will B take to do the work?

    • A) 16 days
    • B) 18 days
    • C) 15 days
    • D) 20 days

    Answer: 16 days

    Explanation: B is 25% more efficient, so B's rate = 1/20 * 1.25 = 1/16. Hence, B will take 16 days.