engineering intelligence MCQ #297

A is 3 times as fast as B. If A can complete a job in 12 days, how long will it take B to complete the same job?

engineering intelligence MCQ #297

  1. Question 1

    Q1. A is 3 times as fast as B. If A can complete a job in 12 days, how long will it take B to complete the same job?

    • A) 24 days
    • B) 36 days
    • C) 30 days
    • D) 48 days

    Answer: 36 days

    Explanation: If A is 3 times as fast as B, then B will take 3 times as long as A to complete the job. So, B will take 3 * 12 = 36 days.