engineering intelligence MCQ #300

A, B, and C can do a job in 10, 12, and 15 days, respectively. If they work together, how many days will they take to complete the job?

engineering intelligence MCQ #300

  1. Question 1

    Q1. A, B, and C can do a job in 10, 12, and 15 days, respectively. If they work together, how many days will they take to complete the job?

    • A) 4 days
    • B) 5 days
    • C) 6 days
    • D) 8 days

    Answer: 4 days

    Explanation: A's 1 day work = 1 / 10, B's = 1 / 12, C's = 1 / 15.