A is 3 times as fast as B. If A can complete a job in 12 days, how long will B take to complete the same job?
Q1. A is 3 times as fast as B. If A can complete a job in 12 days, how long will B take to complete the same job?
Answer: 36 days
Explanation: If A is 3 times as fast as B, then B will take 3 times as long as A to complete the job. So, B will take 3 * 12 = 36 days.