A is 3 times as fast as B. If A takes 12 days to complete a task, how many days will B take?
Q1. A is 3 times as fast as B. If A takes 12 days to complete a task, how many days will B take?
Answer: 36 days
Explanation: If A is 3 times as fast as B, B will take 3 times as long as A. So, B will take 3 * 12 = 36 days.