If 1 day's work = 1/20, then the time required to finish the job (in days) is:

general math MCQ #1810

  1. Question 1

    Q1. If 1 day's work = 1/20, then the time required to finish the job (in days) is:

    • A) 20
    • B) 10
    • C) 25
    • D) 30

    Answer: 20

    Explanation: If 1/20 of the work is completed each day, the entire job takes 20 days.