general math MCQ #295

A and B together take 6 days to complete a task. B and C together take 12 days to complete the same task. A and C together take 8 days to complete it. If A, B and C are working together, how long does it take for them to complete the task?

general math MCQ #295

  1. Question 1

    Q1. A and B together take 6 days to complete a task. B and C together take 12 days to complete the same task. A and C together take 8 days to complete it. If A, B and C are working together, how long does it take for them to complete the task?

    • A) 4(2/3) days
    • B) 4 days
    • C) 5(1/3) days
    • D) 1(1/3) days

    Answer: 5(1/3) days

    Explanation: Adding all three pair equations: 2(1/A+1/B+1/C) = 1/6+1/12+1/8 = 3/8; combined rate = 3/16; time = 16/3 = 5⅓ days.