If 125 men complete a task in 120 days, how many men are needed to complete the same task in 100 days, assuming they work at the same rate?
Q1. If 125 men complete a task in 120 days, how many men are needed to complete the same task in 100 days, assuming they work at the same rate?
Answer: 150
Explanation: Using the work formula: men × days = constant. 125 × 120 = n × 100, so n = 150 men.