If 12 men can do a piece of work in 10 days, how many men would be required to do the same work in 8 days?

general math MCQ #833

  1. Question 1

    Q1. If 12 men can do a piece of work in 10 days, how many men would be required to do the same work in 8 days?

    • A) 12
    • B) 13
    • C) 14
    • D) 15

    Answer: 15

    Explanation: Total work = 12 × 10 = 120 man-days; to finish in 8 days requires 120 ÷ 8 = 15 men.