If 4 workers finish a job in 9 days, how many days for 6 workers (same rate)?

issb intelligence MCQ #35

  1. Question 1

    Q1. If 4 workers finish a job in 9 days, how many days for 6 workers (same rate)?

    • A) 4
    • B) 6
    • C) 8
    • D) 12

    Answer: 6

    Explanation: Total work = 36 worker-days. Six workers need 36/6 = 6 days.