Candidate A can complete an obstacle course alone in 12 days and Candidate B in 18 days. How many days will they take working together?

issb mathematics MCQ #151

  1. Question 1

    Q1. Candidate A can complete an obstacle course alone in 12 days and Candidate B in 18 days. How many days will they take working together?

    • A) 8 days
    • B) 6 days
    • C) 9 days
    • D) 7.2 days

    Answer: 7.2 days

    Explanation: Their combined daily rate is 1/12 plus 1/18, which equals 5/36 of the course. The full course therefore takes 36/5 days, or 7.2 days.