12 men do work in 9 days. 18 men in?
Question 1
Q1. 12 men do work in 9 days. 18 men in?
Answer: 6 days
Explanation: Total 108 man-days so 108 divided by 18 is 6 days. Work each step carefully; ISSB math rewards accuracy under time pressure.