issb mathematics MCQ #524

A finishes work in 16 days. One day work rate?

issb mathematics MCQ #524

  1. Question 1

    Q1. A finishes work in 16 days. One day work rate?

    • A) 1/12
    • B) 1/14
    • C) 1/16
    • D) 1/18

    Answer: 1/16

    Explanation: One day rate is one divided by total days which is 1/16.