If 12 men finish work in 8 days, 16 men will finish in:

issb mathematics MCQ #54

  1. Question 1

    Q1. If 12 men finish work in 8 days, 16 men will finish in:

    • A) 4 days
    • B) 6 days
    • C) 8 days
    • D) 10 days

    Answer: 6 days

    Explanation: Total work = 96 man-days. 96/16 = 6 days. More workers means less time.