A in 6 days, B in 18 days, C in 36 days together?
Question 1
Q1. A in 6 days, B in 18 days, C in 36 days together?
Answer: 3 days
Explanation: Rates sum to 1/6 plus 1/18 plus 1/36 equals 1/3 so 3 days.