8 workers finish in 15 days. 12 workers finish in?
Q1. 8 workers finish in 15 days. 12 workers finish in?
Answer: 10 days
Explanation: Total 120 man-days so 120 divided by 12 is 10 days. Work each step carefully; ISSB math rewards accuracy under time pressure.