6 workers finish in 20 days. 10 workers finish in?
Q1. 6 workers finish in 20 days. 10 workers finish in?
Answer: 12 days
Explanation: Total 120 man-days so 120 divided by 10 is 12 days. Work each step carefully; ISSB math rewards accuracy under time pressure.